Introduction
The grounds for contesting the arbitral award rendered under Section 31 are outlined in Section 34 of the Arbitration and Conciliation Act[1], 1996. However, the challenge to the award can only be lodged within the three-month limitation period following the date on which it was received. The computation of the limitation period, from the date the award was obtained, is bestowed under Section 34 of the Arbitration Act.
Although an appeal against orders issued under Sections 9, 34, 16, and 17 of the Arbitration and Conciliation Act, 1996 (the “Act”)[2] is allowed under Section 37, this provision does not provide a time limit for bringing such appeals. Nevertheless, section 43[3] explicitly mentions that the Limitation Act, 1963 (the “Limitation Act”) shall apply to arbitrations in the same manner as it does to court proceedings. This paper focuses on whether an arbitration agreement can be invoked to a duration which is transient than the time imposed under Limitations Act.
Key Provisions Overview
- Section 31 – Arbitral Award
- Section 34 – Grounds for Setting Aside Arbitral Award
- Section 37 – Appeals
- Section 43 – Applicability of Limitation Act, 1963
Limitation Period Summary
| Provision | Purpose | Time Limit |
|---|---|---|
| Section 34 | Challenge to Arbitral Award | Three months from date of receipt |
| Section 37 | Appeals against Orders | No specific time limit provided |
| Section 43 | Application of Limitation Act | Same as court proceedings |
Contract In Contradiction To Limitation Act
Section 28[4] of the law as it stood before amendment stated that:
“No one can contract himself out of the statute of limitations and consequently where the result of a compromise is that the legal limitation is extended it is open to the judgment debtor to plead that the decree-holder’s application was barred by time.” Section 28 of the Contract Act only takes effect when a term of limitation is shortened. It does not apply when the term expressly states that the plaintiff’s right to bring a lawsuit has been terminated or that the defendant is no longer liable for the claim. Any voluntary agreement to shorten the statute of limitations is void.
This section also discusses agreements to avert legal action. If an agreement attempts to totally prevent a party from exercising his rights under a contract using customary judicial procedures, it is deemed invalid. Although this is regarded as a crucial right for the parties, it is not thought to be of an absolute character. The section contains exceptions as a result of this. The section examines all other contracts with the exception of those with arbitration clauses for pursuing claims and those that refer to ongoing contractual issues through arbitration.[5]
Key Principles Under Section 28
- No party can contract out of the statute of limitations
- Agreements shortening limitation periods are void
- Agreements completely restricting legal proceedings are invalid
- Exceptions exist, particularly for arbitration clauses
Arbitration As Exception
It is clear from the review of the legal situation that arbitration is an exception to the application of Section 28. Therefore, whether arbitration agreements are bound by the typical restrictions imposed by statutory limitations is answered via various judicial interpretations. The discussion follows attempts to explain the complex relationship between Section 28 and how limitation periods apply to arbitration.
Right Versus Remedy
Surprisingly, before the amendment took place, a clause in a contract stated that all advantages or rights would be lost unless a lawsuit was filed within a certain time frame and was not considered a violation of the provision.
- The agreement that was affected by section 28 was one that simply gave up the right to sue.
- It stipulated that any lawsuits must be filed within a certain window of time.
In the proposed amendment, it was emphasized that while a clause terminating a right is valid, one restricting a remedy is not.
The commission suggested amending section 28 of the Contract Act to make terms in contracts that terminate rights arising from and pursuant to the contract upon the expiration of a certain period void in order to remedy this issue.
On January 18, 1997, the Contract Act was changed to make stipulations that:
- limit the enforcement of rights under or pertaining to any contract, and
- extinguish the rights of the parties invalid.
This modification equated the extinguishment of a right with the extinguishment of a remedy.[6]
Pre-1997 Position
Before Section 28 was modified in 1997, agreements that shortened the statute of limitations were distinguished from those that did not restrict the amount of time a party could exercise his rights but instead provided for a release or forfeiture of those rights in the event that no lawsuit was filed within the time frame specified in the agreement.
- Agreements shortening limitation period → considered invalid.
- Agreements providing forfeiture of rights → considered valid.
The latter class of agreements, which fell outside the purview of the section, were deemed to be enforceable between the parties.
Supreme Court Distinction
The Supreme Court made a clear distinction between:
| Type of Agreement | Legal Position |
|---|---|
| Agreement that shortens the statute of limitations | Declared invalid for violating Section 28 |
| Agreement providing forfeiture/waiver of rights if no action is taken | Not hit by Section 28 and considered valid |
This distinction was clarified in National Insurance Co. Ltd. v. Sujir Ganesh Nayak & Co.[7]
In light of Section 28, it was determined that:
- Shortening the statute of limitations was not permitted.
- If the right was not exercised within the allotted time, it might still be terminated.
Inception Of Cause Of Action
To evaluate the limitation period for invoking an arbitration agreement, it is necessary to be acquainted with the term “cause of action”.
Limitation Period Under Article 137
As per article 137 of the Limitation Act[8], the limitation term is three (3) years from the date the right to apply arises for any other application for which no period of limitation is stipulated elsewhere in the provisions.
- The Arbitration Act does not provide any time limit for initiating or reiterating arbitration procedures.
- In such cases, Article 137 acts as a residual clause.
Due to this, arbitration must be started within three years of the date the claimant’s claims were initially denied.
Meaning Of Cause Of Action
The word “cause of action” is used to refer to bringing a legal action against a party in a suitable court of law for any civil violation.
The term “cause of action” is ambiguous, but Russell on Arbitration[9] clarifies it by stating that:
- The limitation period begins from the date the cause of arbitration accrued.
- Or from the date the claimant first acquired:
- A right to sue, or
- A right to demand arbitration.
The claim may expire before the party even realizes it if they merely postpone delivering a notice requesting reference as required by the Arbitration Act because they are unsure of when the cause of action commenced.
Judicial Interpretation
In Panchu Gopal Bose v. Board of Trustees for the Port of Calcutta[10], it was determined that:
- The “cause of arbitration” relates directly to the “cause of action”.
- The limitation period begins when the cause of arbitration accrues.
The statute of limitations for starting an arbitration proceeding begins to lapse from:
- The day the cause of arbitration accrued, or
- The date the claimant first obtained:
- A right to sue, or
- A right to demand arbitration.
As a result:
- The limitation period for arbitration begins on the date the cause of action would have accrued in the absence of the arbitration provision.
- A claim cannot be brought in arbitration after the limitation period, just like in civil proceedings.[11]
Restriction on Arbitration Invocation Beyond the Limitation Act
In the case of Grasim Industries Ltd v. State of Kerala[12], the appellant, Grasim Industries Ltd., was in the Kozhikode District of the State of Kerala producing rayon grade wood pulp. For the exclusive right and license to fell, cut, and remove bamboo from specific regions in the Nilambur valley in order to turn them into rayon grade wood pulp and related goods, the appellant corporation secured various grants from the Keralan government.
On May 3, 1958, the first of these contractual agreements was signed. Supplementary contract agreements dated 06.08.1962, 10.07.1974, 16.11.1976, and 27.10.1988 came after the same.
Arbitration Clause and Legal Issue
- Disputes originating under the first agreement, dated 03.05.1958, were to be resolved through arbitration, according to clause 16.
- An appeal was filed before the Supreme Court due to the failure to request the formation of an arbitral tribunal within the time frame specified in the arbitration agreement.
Court Observation in Grasim Case
While passing the judgment the court held that “Unambiguously, Section 28(b) [of the Contract Act, 1872] states that a contract that terminates a party’s right after a predetermined period of time is void. As a result, even if a limited time limitation for bringing an arbitration dispute has been stipulated (as found in the challenged decision), the provision would be void.”
Sagar Construction v. Govt. of NCT of Delhi
In another case of Sagar Construction v. Govt. of NCT of Delhi[13] construction work had been given to Sagar Constructions, which then invoked the arbitration provision after the Delhi government failed to disburse the funds in accordance with the contract’s agreed-upon provisions.
Issue: Invocation Time Limit
- Sagar Constructions had not invoked the Dispute Resolution Clause within 120 (one hundred and twenty) days of the date the Final Bill was prepared.
- The request to appoint an arbitrator was denied based on this clause.
Delhi High Court Ruling
- A party cannot limit another party’s ability to request arbitration to a shorter time frame than that allowed by the Arbitration Act.
- The parties cannot limit the ability to arbitrate to less than three years from the date the cause of action accrues.
- The Indian Contract Act, 1872 declares unenforceable any agreement that shortens the statute of limitations.
As a result, the HC selected a solitary arbiter.
Municipal Corporation of Delhi v. Natraj Construction Company
Recently, the Delhi high court in the case of Municipal Corporation of Delhi v. Natraj Construction Company[14] addressed this issue.
Case Background
- MCD issued a tender for providing and installing a retro-reflective sign board.
- The contract was awarded to Natraj Construction Company.
- Three months were allotted for project completion.
- Natraj completed the work within the allotted time.
- The bill was sanctioned but payment was withheld due to a CBI FIR alleging poor quality work.
Arbitration and Award
- Natraj invoked arbitration for unpaid dues.
- An arbitral award was passed in its favour.
- The award included:
| Component | Details |
|---|---|
| Work Payment | Amount for completed work |
| Earnest Money | Refund ordered |
| Interest | 15% per annum |
MCD’s Argument
- Disputes had to be raised within 120 days.
- Natraj initiated arbitration after this period.
- Therefore, the claim was time-barred.
Court Decision
The Court determined that MCD’s argument to limit the period of limitation for exercising the arbitration clause to 120 days was without merit and bad in law.
- Relied on Section 28 of the Contract Act[15]
- Relied on Supreme Court decisions:
- Pandit Construction Company v. Delhi Development Authority & Anr[16]
- M/s. Smart Commodity Broker Pvt. Ltd. v. Beant Singh[17]
The Court further stressed that it must not re-evaluate the merits as an appellate court under Section 37 of the Arbitration Act[18].
Key Legal Principles Summary
| Principle | Explanation |
|---|---|
| Section 28, Contract Act | Invalidates agreements restricting legal remedies within shorter periods |
| Limitation Period | Minimum 3 years for arbitration invocation |
| Party Autonomy | Cannot override statutory limitation laws |
| Judicial Role | Courts protect fairness and statutory rights |
Conclusion
The review of pertinent provisions and case law outlines how statutory limitations are imposed and is acting as an exception to the theory of party autonomy in contract, which is a cornerstone of any type of agreement.
It is clear that parties to an arbitration agreement are prohibited from extending beyond the limitations imposed by the Limitation Act or abridging the time limits that have been incorporated in the legislations.
Although intended to protect the parties’ statutory rights, this restriction does add some measure of constraint. Nevertheless, there is a must to provide clarity in the exercise of such rights.
The paradox is created by the conflict between legal protections and arbitration’s fundamental goal of speedy dispute settlement.
Adopting arbitration is driven mostly by the need to streamline dispute settlement procedures, particularly in terms of time efficiency.
It is crucial to recognize the need for statutory observance as well as the primary goal of arbitration, quick dispute resolution, in order to strike this difficult balance.
It is important to highlight that these instances serve as a prime example of how prudent interpretation plays a crucial role in providing parties with a means of protecting their rights.
By viewing the situation from a legal perspective, parties are shielded from the imposition of overly severe limitations and are guaranteed the appropriate amount of time as specified by the provisions to invoke the arbitration agreement.
Judicial guidance, as demonstrated in these cases, not only protects the integrity of the arbitration process but also serves as a safeguard, avoiding the limitation of parties’ entitlements and encouraging a fair and equitable framework for conflict settlement. End Notes:
- The Arbitration and Conciliation Act, 1996, Section 34
- The Arbitration and Conciliation Act, 1996
- The Arbitration and Conciliation Act, 1996, Section 43
- Indian Contracts Act, 1872, Section 28
- B.V.R. Sarma, “Agreements which restrain legal proceedings – An analysis”, http://docs.manupatra.in/newsline/articles/Upload/968A00BF-EA62-4871-AF51-AE0DB6F096F1.pdf, Accessed 29 September, 2023
- Rajdutt S. Singh and Srishti Pandey, “Limitation Period Or Claim Period: What Does Exception 3 To Section 28 Of The Indian Contract Act Deal With?”, https://www.mondaq.com/india/government-contracts-procurement–ppp/1216604/limitation-period-or-claim-period-what-does-exception-3-to-section-28-of-the-indian-contract-act-deal-with, Accessed 29 September, 2023
- National Insurance Co. Ltd. v. Sujir Ganesh Nayak & Co., (1997) 4 SCC 366, AIR 1997 SC 2049
- The Limitation Act, 1963, Article 137
- Russell on Arbitration by Anthony Walton (19th Edn.), pp. 4-5
- Panchu Gopal Bose v. Board of Trustees for the Port of Calcutta, (1993) 4 SCC 338
- Ruhini Dey & Parnika Medhekar, “Brief Analysis on the Applicability of Limitation Act at Various Stages of an Arbitral Proceeding Before the Court in India”, https://www.lawsenate.com/publications/articles/BRIEF_ANALYSIS_ON_THE_APPLICABILITY_OF_LIMITATION_ACT_AT_VARIOUS_STAGES_OF_AN_ARBITRAL_PROCEEDING_BEFORE_THE_COURT_IN_INDIA.pdf, Accessed 29 September, 2023
- Grasim Industries Ltd v. State of Kerala, (2018) 14 SCC 265
- Sagar Construction v. Govt. of NCT of Delhi, 2021 SCC OnLine Del 4647
- Municipal Corporation of Delhi v. Natraj Construction Company, 2023 DHC 2054
- The Indian Contract Act, 1872, Section 28
- Pandit Construction Company v. Delhi Development Authority & Anr, 2007 SCC OnLine Del 993
- M/s. Smart Commodity Broker Pvt. Ltd. v. Beant Singh, 2017 SCC OnLine Del 10591
- The Arbitration and Conciliation Act, 1996, Section 37


