A Case Note on Mohammed Khaleel (D) Through LRs & Ors. v. Jayamma 2026 INSC 651 (Civil Appeal No. 2187 of 2011)
Decided on: June 23, 2026
Court: Supreme Court of India
Bench: Justice Prashant Kumar Mishra & Justice N.V. Anjaria
Core Statute: Section 16(c), Specific Relief Act, 1963
I. Introduction
The Supreme Court’s decision in Mohammed Khaleel (D) Through LRs & Ors v. Jayamma is a landmark reminder that the equitable remedy of specific performance is reserved for the vigilant, not the speculative.
- A plaintiff must prove — with contemporaneous and credible evidence — continuous readiness and willingness to perform his part of the agreement.
- Assertions in pleadings or financial documents produced years later are insufficient.
This judgement upheld the Karnataka High Court’s reversal of a trial court decree for specific performance and dismissed the appeal. It enforces Section 16(c) of the Specific Relief Act, 1963, by requiring readiness and willingness to be proved through timely, reliable evidence.
The case also highlights the intersection of delay and equity: even if filed within limitation, unexplained delay can itself evidence lack of readiness and willingness, disentitling the plaintiff to equitable relief.
II. Factual Background
A. The Agreement and Its Terms
| Parties | Date | Subject Matter | Consideration | Earnest Money | Balance Payment |
|---|---|---|---|---|---|
| Mohammed Khaleel (Purchaser) & Jayamma (Vendor) | December 20, 1990 | Vacant site | Rs. 300,000 | Rs. 25,000 | Rs. 275,000 within 4 months |
The vendor handed over original title documents to the purchaser.
B. Breakdown of Relations and Rescission
- Purchaser insisted on formation of an approach road and demarcation of property.
- Vendor denied such understanding, claiming an existing road sufficed.
- Legal notices exchanged in early 1991.
- The vendor rescinded the agreement and forfeited earnest money, citing the following:
- Failure to obtain ULCRA permissions.
- Imposition of conditions not in agreement.
- Purchaser delayed suit filing by nearly 2 years and 9 months.
C. Litigation History
- Trial court decreed specific performance in favour of purchaser.
- Karnataka High Court reversed, citing failure to prove continuous readiness and willingness under Section 16(c).
- The purchaser’s legal representatives appealed to the Supreme Court (Civil Appeal No. 2187 of 2011).
- The Supreme Court dismissed the appeal on June 23, 2026 — fifteen years after filing.
III. Contentions of the Parties
A. Appellants (Purchaser’s Legal Representatives)
The appellants advanced four principal arguments before the Supreme Court:
- They had financial capacity and produced four Fixed Deposit Receipts (FDRs) totalling Rs. 280,000 to demonstrate availability of funds.
- The demand for property demarcation and an approach road was a legitimate and reasonable step to ensure clear title and access, not an attempt to impose extra-contractual conditions.
- The responsibility to obtain ULCRA permission was primarily that of the vendor/seller, not the purchaser; the purchaser should not be penalised for the vendor’s failure to fulfil this obligation.
- The suit had been filed within the statutory limitation period under Article 54 of the Limitation Act, 1963, and the court was therefore bound to entertain it.
B. Respondent (Vendor)
The respondent countered each of these arguments with persuasion:
- The four FDRs relied upon by the appellants were dated 1999 and 2001 — approximately eight to ten years after the date of the agreement in 1990 and five to seven years after the suit was filed in 1993. They were therefore wholly incapable of proving financial readiness during the contractually relevant period, namely the four-month window for payment in 1990-91.
- The purchaser had remained passive regarding the ULCRA compliance process, failing to furnish the necessary affidavits and documents that were required from his side for obtaining the permission. Obtaining ULCRA clearance was a bilateral obligation, and the purchaser had not played his part.
- The delay of two years and nine months between the vendor’s clear rescission of the agreement and the filing of the suit was wholly inconsistent with the conduct expected of a person who claimed to be continuously ready and willing to perform a contract.
IV. Statutory Framework
A. Section 16(c) of the Specific Relief Act, 1963 — The Governing Provision
Section 16 of the Specific Relief Act, 1963, enumerates the circumstances in which specific performance cannot be enforced. Clause (c), which was directly in issue in this case, reads thus:
“Specific performance of a contract cannot be enforced in favour of a person—(c) who fails to aver and prove that he has performed or has always been ready and willing to perform the essential terms of the contract which are to be performed by him, other than terms the performance of which has been prevented or waived by the defendant.”
The Explanation to Section 16(c) is equally important. It provides that:
| Provision | Explanation |
|---|---|
| (i) | Where a contract involves payment of money, it is not essential for the plaintiff to actually tender money to the defendant or deposit it in court, except when directed by the court. |
| (ii) | The plaintiff must aver performance of, or readiness and willingness to perform, the contract according to its true construction. |
The explanation thus makes clear that the law does not demand the futile gesture of a physical tender of money at every stage. What is demanded is proof of the capacity and intention to pay, through credible contemporaneous evidence.
B. Section 20 and the 2018 Amendment
Prior to the Specific Relief (Amendment) Act, 2018, Section 20 of the Specific Relief Act vested courts with a general discretion to refuse specific performance, even to a plaintiff who had proved all statutory requirements. The 2018 amendment substituted Section 20, making specific performance a statutory right in certain cases while preserving the court’s power to substitute damages.
However, Section 16(c) — the personal bar provision — remains intact and unchanged. Courts have consistently held that regardless of the 2018 amendment, a plaintiff who fails to prove readiness and willingness under Section 16(c) cannot obtain specific performance, since this is a condition precedent, not a discretionary consideration.
predateThe present case was governed by the pre-amendment provisions, as the agreement and suit pre-date 2018. The Court applied the well-settled pre-amendment jurisprudence.
C. Article 54, Limitation Act, 1963
Article 54 of the Limitation Act prescribes that a suit for specific performance must be filed within three years from the date fixed for performance, or if no date is fixed, from the date when the plaintiff has notice that the defendant has refused to perform.
Filing within the limitation period is a necessary condition, but — as this judgement emphatically holds — it is not a sufficient one. The plaintiff’s conduct in the interval between the breach and the suit is itself relevant to the question whether he has been continuously ready and willing.
V. The Judgment: Analysis of Holdings
A. The Distinction Between Readiness and Willingness
The Bench reiterated and applied the settled distinction between the twin requirements of Section 16(c). ‘Readiness’ refers to the financial capacity of the plaintiff to perform the contract — that is, his ability to pay the agreed consideration. Willingness, on the other hand, concerns the conduct and intention of the plaintiff — whether he genuinely intended to proceed with the transaction and took active steps to do so.
- Both elements must be pleaded and proved. They are not alternatives.
- A plaintiff with financial means but equivocal conduct fails on willingness.
- A plaintiff with impeccable conduct but lacking funds fails on readiness.
The Court held that the plaintiff in this case failed on both counts.
B. Rejection of Post-Suit Financial Documents
The central evidentiary finding of the judgement is that the four FDRs produced by the appellants were created in 1999 and 2001, whereas the agreement was executed in December 1990 and the suit was filed in 1993. These documents therefore post-dated the suit by six to eight years and the agreement by nearly a decade. The Court categorically held that such documents cannot prove financial readiness at the time of the agreement, within the four-month contractual window, or even at the time of institution of the suit.
This holding establishes an important evidentiary principle: financial documents offered to prove readiness must be contemporaneous with the relevant transactional period. Documents created after litigation has begun — or years after the suit was filed — are inherently suspect.
- No material showed the balance sale consideration of Rs. 275,000 was available at the time of the agreement.
- No proof within the four-month performance period.
- No proof at the time of filing the suit.
C. ULCRA Compliance: A Bilateral Obligation
The vendor had rescinded the agreement partly on the ground that the purchaser had failed to obtain ULCRA permission. The appellants argued that this was primarily the vendor’s obligation. The Court did not fully accept this argument.
ULCRA compliance required participation from both parties – including affidavits and documents by the purchaser. The Court found that the purchaser’s passive conduct in the ULCRA process was an additional indicator of his lack of readiness and willingness.
A plaintiff who sits back while statutory permissions remain unobtained, without taking required steps, cannot credibly claim continuous readiness and willingness.
D. Delay as a Reflection of the Absence of Continuous Readiness
The Court devoted considerable attention to the plaintiff’s delay in filing the suit. The agreement was dated December 1990. The vendor rescinded it in early 1991. The suit was not filed until 1993 — a gap of approximately two years and nine months.
While this delay was within the three-year limitation period prescribed by Article 54, the Court held that it was nonetheless inequitable and reflected a lack of urgency inconsistent with the claim of continuous readiness.
“This conduct of the appellant/plaintiff, in our view, reflects lack of continuous readiness and willingness to perform his part of the contract, which is a sine qua non for the grant of relief of specific performance.”
The Court relied on N.P. Thirugnanam v. Dr R. Jagan Mohan Rao to hold that specific performance, being an equitable remedy, requires promptness. A plaintiff aware of refusal cannot wait years before approaching the court while claiming readiness and willingness.
VI. The Precedential Architecture
The ruling sits within a rich and well-settled body of Supreme Court authority on Section 16(c). The following cases constitute the principal landmarks:
| Case | Principle / Relevance |
|---|---|
| N.P. Thirugnanam v. Dr R. Jagan Mohan Rao, (1995) 5 SCC 115 | Readiness and willingness must be continuous from contract to decree. Filing within limitations is insufficient. |
| Saradamani Kandappan v. S. Rajalakshmi, (2011) 12 SCC 18 | Timely performance and contractual time frames are crucial, even if time is not expressly of the essence. |
| Man Kaur (Dead) v. Hartar Singh Sangha, (2010) 10 SCC 512 | The burden of proving readiness and willingness lies on the plaintiff; bare averments are insufficient. |
| Sita Ram v. Radhey Shyam, (2007) 12 SCC 10 | Reaffirmed readiness (financial capacity) vs willingness (conduct). Equivocal conduct bars relief. |
| Pydi Ramana v. Ramulu, Davarasety Manmadha Rao, 2024 INSC 507 | Recent reiteration that continuous readiness and willingness are conditions precedent to specific performance. |
| C. Haridasan v. Anappath Parakkattu Vasudevakurup, 2023 (SC) | Readiness and willingness must be demonstrated through conduct and payment timelines, not plaint averments. |
| K.S. Vidyanadam v. Vairavan, (1997) 3 SCC 1 | Contractual timeframes are critical; failure to act promptly indicates lack of willingness. |
| Mehboob-Ur-Rehman v. Ahsanul Ghani, (2019) 4 SCC 526 | The 2018 amendment to Section 20 does not dilute Section 16(c). Personal bar operates independently. |
| R. Kandasamy v. T.R.K. Sarawathy, 2024 LiveLaw (SC) 911 | Denied specific performance due to financial incapacity, reluctance to pay, and unjustified delays. |
VII. Equity, Delay and the Conduct of the Plaintiff
Specific performance is not a remedy that follows automatically from a breach of contract. It is an equitable remedy, historically rooted in the jurisdiction of equity courts. Even after the 2018 amendment to the Specific Relief Act, which removed the general discretion of courts under the unamended Section 20, the remedy retains its equitable character insofar as the plaintiff’s own conduct remains a decisive factor under Section 16(c).
Delay as an Indicator
The Court in this case treated the plaintiff’s delay of nearly three years before filing the suit as a significant indicator of the absence of continuous readiness and willingness. This is an important doctrinal development. It means that delay — even if legally excusable under the Limitation Act — is not factually irrelevant.
- Courts will scrutinise what the plaintiff was doing during the interval between the breach and the suit.
- If the answer is inactivity — no notices, no tenders, no legal steps, no urgency — that inactivity itself is evidence against his claim of readiness and willingness.
Equitable Principle
The equitable principle underlying this approach is the maxim that equity aids the vigilant, not the indolent. A plaintiff who was truly aggrieved by the vendor’s refusal to execute the sale deed, and who had the means to perform, would ordinarily be expected to act with dispatch.
Prolonged silence raises a legitimate inference that the plaintiff was indifferent to the contract, perhaps waiting for property values to rise. The suit, when ultimately filed, may appear as an attempt to capitalise on subsequent appreciation in land values rather than genuine enforcement.
VIII. Impact of the 2018 Amendment to the Specific Relief Act
The Specific Relief (Amendment) Act, 2018, introduced significant structural changes to the remedial framework for breach of contract. The principal changes relevant to specific performance were the following:
| Provision | Change Introduced |
|---|---|
| Section 10 | Specific performance became a statutory remedy as a rule, rather than discretionary, for immovable property contracts. |
| Section 20 | Introduced substituted performance, allowing third-party execution at the promisor’s cost. |
| Section 16(c) | Unchanged, it continues to impose a personal bar requiring continuous readiness and willingness. |
The present case was governed by pre-amendment provisions, but the reasoning on readiness and willingness applies equally under the amended Act.
IX. Evidentiary Implications: What Proof Is Required?
This judgement raises the practical evidentiary bar in suits for specific performance. Plaintiffs and counsel must carefully consider what evidence is required and when it must have been created.
A. Contemporaneity of Financial Documents
- Financial documents must be contemporaneous with the transactional period.
- Evidence should show funds were available:
- At the time, balance consideration fell due.
- At the time of or shortly before filing the suit.
- Ideally, at all material times in between.
- Documents created after filing are vulnerable to attack as manufactured evidence.
B. Active Conduct as Evidence of Willingness
Willingness must be evidenced by conduct, not just averments. Valuable evidence includes the following:
- Legal notices issued promptly after refusal.
- Correspondence showing readiness to pay balance consideration.
- Steps taken to facilitate registration (e.g., visits to Sub-Registrar).
- Participation in statutory compliance processes (ULCRA, RERA).
- Absence of extra-contractual demands or deviations.
C. Prompt Filing
The plaintiff should file the suit promptly after refusal. While Article 54 permits three years, unexplained delay undermines readiness and willingness. Any delay must be credibly explained with evidence.
D. The Physical Tender Requirement
Section 16(c) exempts plaintiffs from physically tendering balance consideration unless directed by the court. However, exemption from tender does not mean exemption from proof of financial capacity. Plaintiffs must demonstrate funds through documentary and oral evidence.
X. Drafting Guide: The Well-Pleaded Specific Performance Suit
In light of this judgement, advocates filing suits for specific performance should ensure that the plaint covers the following elements expressly and in detail:
Narrative of Financial Capacity
- Expressly state the plaintiff’s financial position at the time of the agreement, within the contractual performance window, and at the time of filing.
- Identify the source of funds (savings, FDRs, bank deposits, income).
- Annex relevant bank statements or FDR receipts as documents to the plaint.
Chronological Conduct Narrative
- Set out a clear, chronological narrative of every step taken by the plaintiff from the date of the agreement to the date of the suit.
- Include payment of earnest money, receipt of title documents, correspondence with the vendor, notices calling upon the vendor to execute the sale deed, and the vendor’s responses or silence.
Explanation of ULCRA/ Regulatory Compliance
- If statutory permission was required, state what steps the plaintiff took.
- Clarify what steps the vendor was required to take and what actually happened.
- Do not leave the regulatory compliance narrative incomplete.
Explanation of Delay
- If there is any delay between the vendor’s refusal and the filing of the suit, explain it concretely.
- Possible reasons: pursuing out-of-court settlement, correspondence during this period, bereavement, or incapacity.
- Silence on delay will be used against the plaintiff.
Averment in Terms of Section 16(c)
The plaint must contain an express averment that the plaintiff has always been ready and willing to perform the essential terms of the contract, including payment of the balance consideration, and that he remains so ready and willing on the date of the suit.
No Extra-Contractual Conditions
- Ensure the plaint does not inadvertently disclose that the plaintiff sought to impose conditions not agreed in the contract.
- Any demand for approach roads, boundary walls, demarcation, ULCRA permissions (where the obligation was the vendor’s alone), or other extras not stipulated in the agreement will be used to deny relief.
XI. Lines of Defence for Defendants
For a defendant resisting a suit for specific performance, this judgement offers a strengthened arsenal:
| Defence Strategy | Explanation |
|---|---|
| Challenge Financial Documents | Reject FDRs, bank statements, or records created after the suit or inconsistent with the transactional timeline. |
| Scrutinise Conduct | Highlight inactivity, silence, or failure to send notices during the performance period or breach-to-suit interval. |
| Extra-Contractual Concessions | Plead deviations such as demands for approach roads as evidence of unwillingness to perform the contract. |
| Equitable Delay Arguments | Raise delay even within limitation as evidence against continuous readiness. |
| Speculative Property Claims | Argue the suit is speculative, exploiting rising land values rather than bona fide enforcement. |
XII. Special Significance in Property Disputes
The Supreme Court drew attention to a practical reality in Indian property litigation: agreements to sell are often kept alive speculatively, with purchasers deferring enforcement until property values rise sufficiently to make litigation economically worthwhile.
When the suit is ultimately filed, plaintiffs retroactively construct a narrative of continuous readiness, often supported by documents created for the purpose.
Court’s Doctrinal Framework
- Financial documents must be contemporaneous.
- Delay is treated as evidence of absence of willingness.
- Speculative plaintiffs face greater difficulty in obtaining specific performance.
Urban Land Market Impact
The ruling is particularly relevant in urban land markets, where the gap between agreement value and prevailing market value can be enormous by the time of decree. The Supreme Court’s insistence on contemporaneous evidence is a proportionate corrective to speculative litigation incentives.
XIII. Summary of Legal Propositions
The following propositions may be extracted from this judgement and the body of authority cited in it:
| Legal Proposition | Description |
|---|---|
| 1 | Section 16(c) of the Specific Relief Act, 1963, imposes a personal bar: a plaintiff who fails to aver and prove continuous readiness and willingness cannot obtain specific performance. |
| 2 | ‘Readiness’ means financial capacity to perform the contract, especially to pay the agreed consideration. ‘Willingness’ means the conduct and bona fides of the plaintiff in pursuing the contract. |
| 3 | Both readiness and willingness must be continuous from the date of the agreement to the date of the decree. |
| 4 | Financial documents offered to prove readiness must be contemporaneous with the relevant transactional period. Documents created after the filing of the suit cannot prove readiness at the time of the agreement or at the time of the suit. |
| 5 | A plaintiff need not physically tender the balance consideration or deposit it in court but must still produce credible evidence of financial capacity. |
| 6 | Delay in filing the suit, even if within the limitation period prescribed by Article 54, is relevant to the question of continuous readiness and willingness. Unexplained delay negates the claim. |
| 7 | A plaintiff who imposes extra-contractual conditions or remains passive in the face of a statutory compliance obligation he is required to fulfil demonstrates an absence of willingness. |
| 8 | Specific performance is an equitable remedy. The plaintiff must approach the court promptly and with entirely clean hands. Equity aids the vigilant, not the indolent. |
| 9 | The personal bar under Section 16(c) operates independently of the discretionary framework of Section 10/20 and the 2018 amendment. Even where specific performance is otherwise available as a statutory remedy, a plaintiff who fails Section 16(c) cannot succeed. |
| 10 | Courts will scrutinise suits for specific performance in property disputes with particular care to ensure they are genuine contractual enforcement actions and not speculative claims based on post-agreement appreciation of property values. |
XIV. Conclusion
Mohammed Khaleel (D) Through LRs & Ors. v. Jayamma does not alter the substantive law governing specific performance. What it does is enforce that law with a rigour and clarity that the courts have sometimes been reluctant to apply in practice. The judgement is a principled restatement of a well-settled rule: that the readiness and willingness mandated by Section 16(c) of the Specific Relief Act, 1963, must be real, continuous, and proved through contemporaneous evidence — not reconstructed from documents manufactured after the dispute has crystallised into litigation.
Key Lessons
- Financial documents: Must be tied to the relevant transactional timeline; FDRs created years after the suit was filed are worth nothing as proof of readiness at the time of the agreement.
- Delay in filing: A plaintiff who waits years after the defendant’s refusal before filing suit cannot expect the court to treat him as a person who was always ready and willing.
- Active participation: Active involvement in all obligations required of the plaintiff under the contract — including statutory compliance processes — is necessary; passivity is fatal to the claim.
Practical Implications
For property practitioners, this judgement is a checklist for both offence and defence:
- Plaintiffs: Must gather and preserve contemporaneous evidence from the moment a dispute looms.
- Defendants in receipt of a specific performance summons must immediately examine whether the plaintiff’s financial evidence is contemporaneous and whether his conduct between the breach and the suit is consistent with the claim of continuous readiness.
The court has handed both sides a sharp analytical tool. How well they use it will determine the outcome of the next generation of specific performance battles.
Disclaimer
This article is intended for academic and professional reference only. It does not constitute legal advice.

