The Supreme Court’s judgment in V.N.A.S. Chandran v. S. Venilla & Ors. (Neutral Citation: 2026 INSC 776; decided on July 31, 2026) reaffirms a cardinal principle of equity jurisprudence: a decree for specific performance is not an automatic entitlement flowing from a valid contract, but a discretionary relief contingent upon the plaintiff’s continuous readiness and willingness to perform, coupled with conduct that does not offend the conscience of the court.
I. Factual Matrix and Judicial Journey
The dispute arose from an Agreement to Sell dated April 1, 2004, under which the appellant, V.N.A.S. Chandran, agreed to sell property at Udhagamandalam (Ooty) for a recorded consideration of ₹2.25 crore — though the appellant maintained the true price was ₹2 crore, the higher figure having been recorded to help the purchaser’s husband raise funds.
On the same day, the appellant executed a General Power of Attorney in the purchaser’s husband’s favour.
The purchasers paid an advance of ₹85 lakh. The sale was to complete within sixty days of an ex parte preliminary decree in a pending partition suit being set aside.
Disputes subsequently arose over:
- Balance payment.
- Revocation of the Power of Attorney.
- A further agreement the appellant entered into with a third party.
Trial Court Findings
The Trial Court found ₹85 lakh had been paid as an advance. It ordered:
- Refund of the advance with 15% interest.
- A charge over the property under Section 55(6)(b) of the Transfer of Property Act, 1882.
However, it refused specific performance, holding the plaintiffs had not approached the court with clean hands.
High Court Decision
The Madras High Court (A.S. No. 443 of 2008) reversed this refusal and decreed specific performance, relying substantially on a demand draft for ₹1.40 crore produced only in 2011, at the close of appellate hearing.
Supreme Court Ruling
The Supreme Court (Prashant Kumar Mishra and N.V. Anjaria, JJ.) allowed the appeal and restored the Trial Court’s decree.
| Court | Key Finding |
|---|---|
| Trial Court | Refund of ₹85 lakh with 15% interest; charge under Section 55(6)(b); specific performance refused. |
| Madras High Court | Reversed trial court and granted specific performance. |
| Supreme Court | Allowed appeal and restored the trial court decree. |
II. Legal Framework: Section 16(c) of the Specific Relief Act, 1963
Section 16(c) of the Specific Relief Act, 1963, as it stood prior to the 2018 amendment, bars specific performance in favour of a plaintiff who fails to aver and prove continuous readiness and willingness to perform the essential terms of the contract.
Explanation (ii) to clause (c) clarifies that in contracts involving payment of money, actual tender is not essential unless the court directs it — but the plaintiff must still demonstrate financial capacity and genuine intent to perform.
The continuous readiness and willingness on the part of the plaintiff is a condition precedent to granting the relief of specific performance. This circumstance is material and relevant and is required to be considered by the court while granting or refusing to grant the relief. If the plaintiff fails to either aver or prove the same, he must fail.
— N.P. Thirugnanam v. Dr. R. Jagan Mohan Rao, (1995) 5 SCC 115, at para. 5
III. Readiness and Willingness: Distinct, Conjunctive, and Continuous
The Supreme Court has consistently distinguished between readiness and willingness. Although closely related, they are separate legal requirements that must coexist throughout the transaction.
Readiness — Financial Capacity to Perform
- Availability of funds.
- Demonstrable ability to raise funds promptly.
- Financial capacity at every material point in time.
Willingness — Conduct and Mental Disposition
- Genuine eagerness to complete the transaction.
- Conduct reflected through pleadings.
- Correspondence demonstrating intention.
- Behaviour before and after institution of the suit.
Both Requirements Are Mandatory
Both limbs are indispensable and cumulative; failure in either disentitles the plaintiff to equitable relief.
In Kamal Kumar v. Premlata Joshi, the Court restated the governing three-fold enquiry:
- Whether a valid and concluded contract exists.
- Whether the plaintiff has been, and remains, ready and willing to perform.
- Whether the plaintiff has in fact performed his part of the contract, and if so, in what manner and to what extent.
IV. The Supreme Court’s Reasoning in Chandran
A. Discontinuous Readiness and Willingness
The Bench held that readiness and willingness must be continuous from the date of the agreement until the decree — not merely established at some intervening point.
On the facts:
- Production of a ₹1.40 crore demand draft in 2011, seven years after the agreement, did not establish continuous financial readiness.
- Two earlier cheques for ₹25 lakh and ₹5 lakh had been dishonoured for insufficient funds.
- The purchasers sold their own Chennai properties only in May 2006, after the September 2005 suit was filed, showing they lacked funds at the point of institution.
- A Memorandum of Understanding relied upon for raising funds was mentioned in neither the legal notice nor the plaint.
In the suit for specific performance, the plaintiffs had to show their means i.e., availability of funds and readiness and willingness continuously at all material points of time i.e., soon after the agreement till the execution of the decree.
— V.N.A.S. Chandran v. S. Venilla, 2026 INSC 776
B. Conduct Disentitling Equitable Relief
The Court found the purchasers’ conduct independently disinterested.
- One purchaser lodged a criminal complaint at Madurai seeking recovery of the advance while simultaneously pursuing specific performance of the same agreement.
- The Court declined to excuse this as a mere “counterblast,” observing that retaliatory criminal proceedings of this kind are generally to be censured rather than indulged.
- The purchasers also took mutually irreconcilable positions on whether contractual rights had been assigned to a third party.
The complaint itself being a ‘counterblast’ is no excuse in law; in fact, courts generally censure these kinds of retributive criminal proceedings.
— V.N.A.S. Chandran v. S. Venilla, 2026 INSC 776
C. Long Lapse of Time as an Independent Factor
The Bench treated the lapse of over two decades since the 2004 agreement as a relevant and independent consideration under Section 20, particularly given the appellant’s advanced age and the intervening death of one purchaser.
Citing Saradamani Kandappan v. S. Rajalakshmi and Nanjappan v. Ramasamy, the Court reiterated that long delay is a discretionary factor, especially where hardship to the defendant is manifest.
Moreover, we cannot ignore the fact that over two decades have passed since the Agreement to Sell was concluded. … Defendant No. 1 is today a man of highly advanced age, and Plaintiff No. 2 has passed away. To compel the transfer of immovable property under these circumstances would not, in our opinion, be equitable.
— V.N.A.S. Chandran v. S. Venilla, 2026 INSC 776
D. A Subsidiary Procedural Holding — Order XLI Rule 22 CPC
The Court also settled, relying on S. Nazeer Ahmed v. State Bank of Mysore, that a respondent who supports a decree may assail a finding adverse to him without filing cross-objections under Order XLI Rule 22 CPC, provided he seeks no relief beyond what the decree already grants.
This is a point of practical value for defendants who prevail below on one ground but wish to sustain the decree on another before the appellate court.
V. Harmonising Precedents: Delay, Limitation, and Discretion
The judgement navigates a deliberate line between apparently competing lines of authority.
Ferrodous Estates Pvt. Ltd. v. P. Gopirathnam held that delay alone, where the suit is filed within limitation, cannot found refusal of specific performance absent laches or other inequitable conduct.
Chandran does not disturb this. It distinguishes such cases on the presence of additional, independently disentitling conduct — discontinuous financial readiness, inconsistent litigation postures, and demonstrable hardship to the defendant — rather than treating delay as per se fatal within limitation.
Key Precedents Relied Upon
| Case | Legal Principle |
|---|---|
| Ferrodous Estates Pvt. Ltd. v. P. Gopirathnam (Dead) & Ors., AIR 2020 SC 5041 | Delay within limitation, without more, is not fatal. |
| Nanjappan v. Ramasamy & Anr., Civil Appeal No. 2373 of 2015 | Extended, repeatedly renegotiated delay coupled with resultant hardship justifies refusal. |
| Saradamani Kandappan v. S. Rajalakshmi & Ors., (2011) 12 SCC 18 | Steep appreciation in property values and consequent hardship are relevant discretionary factors; courts should be wary of suits not filed promptly after breach. |
Doctrinal Position Emerging
Read together, the doctrinal position that emerges is that delay operates on a sliding scale.
- Purely procedural delay within limitation, standing alone, does not defeat relief.
- Delay that is symptomatic of discontinuous readiness, inconsistent conduct, or disproportionate hardship becomes substantive.
- Such delay may independently justify refusal under Section 20 — even where the suit is technically within limitation.
VI. Practical Implications for Litigants and Drafters
The judgement offers several practical lessons for litigants, lawyers, and drafters:
- Maintain contemporaneous documentary proof of financial readiness from the date of agreement — bank statements, sanctioned loan letters, or records of asset sales — rather than relying on funds arranged and produced only during litigation.
- Avoid parallel or inconsistent proceedings (e.g., a criminal complaint for refund of advance filed alongside a suit for specific performance of the same agreement); such conduct will be scrutinised as evidence of abandonment or bad faith, not excused as a mere counterblast.
- Plead readiness and willingness with precision under Section 16(c), and lead evidence covering the entire period from agreement to decree, not merely the date of suit.
- Where representing a defendant supporting a decree on an alternative ground, note that cross-objections under Order XLI Rule 22 CPC are unnecessary if no additional relief beyond the existing decree is sought — S. Nazeer Ahmed applies.
- In drafting agreements to sell, build in explicit timelines, escrow or proof-of-funds mechanisms, and consequences of delay, to pre-empt readiness-and-willingness disputes years down the line.
- Treat long lapse of time as a live discretionary risk even within limitation, particularly where the defendant’s advanced age, death of a party, or steep appreciation in property value would make specific performance inequitable.
VII. Citation Table
| Case / Citation | Proposition Relied Upon |
|---|---|
| V.N.A.S. Chandran v. S. Venilla & Ors., Neutral Citation 2026 INSC 776; 2026 LiveLaw (SC) 758 (SC, 31.07.2026, Mishra & Anjaria, JJ.) | Continuous readiness and willingness must subsist from agreement to decree; a long lapse of time is an independent discretionary factor under Section 20. |
| N.P. Thirugnanam (D) by LRs v. Dr. R. Jagan Mohan Rao & Ors., (1995) 5 SCC 115; AIR 1996 SC 116 | Continuous readiness and willingness is a condition precedent; conduct before and after suit is material. |
| Nanjappan v. Ramasamy & Anr., Civil Appeal No. 2373 of 2015 (SC, 24.02.2015), (2015) 2 SCC 555; R. Banumathi, J. | Extended, repeatedly renegotiated delay and resultant hardship justify refusal of specific performance despite part-payment. |
| Kamal Kumar v. Premlata Joshi & Ors., (2019) 3 SCC 704; AIR 2019 SC 459 (Civil Appeal No. 4453 of 2009) | Threefold test for specific performance: concluded contract, continuous readiness/willingness, and actual performance of plaintiff’s part. |
| Mrs Saradamani Kandappan v. Mrs S. Rajalakshmi & Ors., (2011) 12 SCC 18 | Steep appreciation in property values and consequent hardship are relevant to the exercise of discretion; courts should discourage suits not filed promptly after breach. This is pre-2018-amendment jurisprudence, expressly carried forward in Chandran. |
| Ferrodous Estates (Pvt) Ltd. v. P. Gopirathnam (Dead) & Ors., AIR 2020 SC 5041 (Civil Appeal No. 13516 of 2015, SC, 12.10.2020, Nariman & Navin Sinha, JJ.) | Delay alone, where the suit is within limitation, cannot be found to be a refusal of specific performance absent laches or inequitable conduct. The article’s doctrinal contrast with Chandran is sound: Chandran distinguishes Ferrodous on the presence of additional disentitling conduct, not on limitation. |
| S. Nazeer Ahmed v. State Bank of Mysore, (2007) 11 SCC 75 | A respondent supporting a decree may impugn an adverse finding without filing cross-objections under Order XLI Rule 22 CPC, provided no additional relief is sought. |
| Annamalai v. Vasanthi, (SC) 2025 INSC 1267 decided on 29 October, 2025 | Declaratory relief as to invalidity of termination is unnecessary where termination is mere repudiation and the contract confers no unilateral right to terminate. |
| Major Gen. Darshan Singh v. Brij Bhushan Chaudhary, (SC) 2024 INSC 157 decided on March 1, 2024 | Reiterates the discretionary, equitable character of specific performance under the unamended Act. |
| Muddam Raju Yadav v. B. Raja Shanker, SC 2026 INSC 214 decided on 10 March, 2026 | Reiterates the discretionary, equitable character of specific performance under the unamended Act. |
| A. Shahul Hameed v. N. Malligarjuna, 2026 INSC 573 decided on 27 May, 2026 | Second Appeal Limits: High Courts cannot re-appreciate evidence or overturn concurrent factual findings under Section 100 of the CPC unless those findings show clear perversity or legal error. Readiness and Willingness: Assessed through the overall conduct of parties and total circumstances, not just by the timing of a legal notice, provided the suit is filed within the limitation period. Substantial Compliance: Payment of a major chunk of advance sale consideration (such as 93% here) strongly indicates the buyer’s readiness and willingness. |
| Janardan Das v. Durga Prasad Agarwalla, 2024 INSC 778 decided on 24 September, 2024 | “24. In view of the foregoing analysis, we conclude that the plaintiffs failed to demonstrate their continuous readiness and willingness to perform their contractual obligations, and that Defendant No. 1 lacked the authority to bind Defendant Nos. 6 to 8 in the agreement dated 06.06.1993. Given the incomplete and unenforceable nature of the agreement, we find it neither just nor equitable to grant the relief sought by the plaintiffs.” |
Key Principles Emerging from the Above Authorities
- Continuous readiness and willingness must exist from the date of the agreement until the passing of the decree.
- Specific performance is an equitable and discretionary remedy, not an automatic consequence of a valid contract.
- Delay, coupled with inequitable conduct or hardship, may justify refusal of specific performance.
- The plaintiff’s conduct before, during, and after institution of the suit remains a crucial consideration.
- Financial capacity and substantial compliance are important indicators of readiness and willingness.
- High Courts exercising jurisdiction under Section 100 CPC cannot interfere with concurrent findings of fact unless perversity or legal error is established.
- Courts continue to balance contractual rights with equitable considerations while granting specific performance.
VIII. Conclusion
V.N.A.S. Chandran v. S. Venilla stands as an authoritative reminder that specific performance remains an equitable remedy, not a mechanical entitlement flowing from a valid contract. Courts will scrutinise not only the contract’s validity but the plaintiff’s continuous financial capacity, the consistency of conduct across parallel proceedings, and the equities of delay — including hardship to a defendant of advanced age.
In an era of protracted litigation, the judgement reinforces a proposition of old vintage in equity: relief favours the vigilant, not the dormant.

